1�The pile construction was completed in May, 2007.
2�Casting at the pile end was completed in June, 2007; also, the high-pressure rotary jet grouting pile at east sewage line clearing area was completed.
3�72 rotary jet grouting piles were completed at the south clearing area in July, 2007.
4�Pile construction was completed in October, 2007.
5�State Land Use Certificate was issued by Suzhou People’s Government to Gate of the Orient on October 29, 2007.
6�The off-site temporary roads were constructed in November, 2007.
7�The first specialist forum for the construction proposal of the foundation pit was held on November 15, 2007.
8�Test well was completed in December, 2007.
9�Construction proposal of the foundation pit was approved by the specialists on January 26, 2008.
10�Specialist forum was held again for the construction proposal of the foundation pit’s guard post on February 28.
11�Construction Permission License was issued by Planning & Construction Bureau in Suzhou Industrial Park on March 4, 2008.
12�The personnel from the safety supervision station arrived at the construction site on March 18, 2008 for safety supervision.
13�The personnel from the quality control station arrived at the construction site on March 25, 2008 for quality control. |